PROJECT REPORT
ON:
HYDRAULIC IMPROVMENTS AT BAF
BASES (CRM)
SUBMITTED BY:
1. NEELESH VT20110345
2. RAJEEV RANJAN VT20110909
3. RENSO PURTY VT20110540
UNDER GUIDANCE OF:
Mr. P.KAISER
Senior Manager
BAF/ECL/SPM
-
7/30/2019 Cham Final
2/47
JUNE 2011
CERTIFICATE
This is to certify that following students have successfully
completed the project on
HYDRAULIC IMPROVEMENTS AT BAF BASES
as a part of Vocational Training at CRM complex, TATA
STEEL, Jamshedpur during June14, 2011 to July 5, 2011under our guidance.
They have successfully completed this project and worked
very sincerely to our satisfaction.
1. NEELESH
2. RAJEEV RANJAN
3. RENSO PURTY
Mr. P. KAISER
-
7/30/2019 Cham Final
3/47
Senior Manager
BAF /ECL/SPM
ACKNOWLEDGEME
NT
Outstanding achievement is not possible in
hydraulic. It needs lot of help and assistance besides
a healthy environment, luckily I have.
First and foremost, I would like to express my hearty
thanks and indebtedness to Mr. PERWAIZ KAISERfor his enormous help and encouragement throughout
the project. It would have been impossible for me to
have a clear idea and way of approach without his
support.
I am thankful to all the employees of the department
who stood by my side to help me out in theunderstanding of the concepts and techniques in the
process.
I am also thankful to SNTI department for allowing me
to register for the project.
-
7/30/2019 Cham Final
4/47
CONTENTS:
1. INTRODUCTION
a. About Tata Steel
b. Introduction to Steel
Manufacturing
2. Cold Rolling Mill
a. Introduction
b. Basics
c. Pickling & Tandem Cold Mill
(PLTCM)
d. Batch Annealing Furnace (BAF)
e. Skin Pass Mill (SPM)
f. Galvanizing Lines (CGL)
3. Flow chart of BAF process
4. About Industrial hydraulics
5. Project in BAF hydraulics
6. Hydraulic Circuit in BAF
-
7/30/2019 Cham Final
5/47
7. Procedure of cylinder seal change
8. Internal diameter of clamping
cylinder & seal
9. Observation
9.1 Causes of hydraulic seal fail in
cylinders
9.2 Improvement
10. Solution &Conclusion
-
7/30/2019 Cham Final
6/47
INTRODUCTION:
About Tata Steel
TATA Enterprises with 82 companies and an annual turnoverexceeding US $ 8.8 billion employ more than 262,000 people. Tata
Company has forged a number of global alliances with eminent
international partners in several fields. In terms of capital market
performance as many as 40 listed Tata companies account for
nearly 5% of the total market capitalization of all listed companies.
Tata Steel, the Flagship Company of the Tata Group of Companieswas set up in 1907 by the great visionary and patriot industrialist
Jamshedji Nusserwanji Tata. Ever since its inception, the steel
company has upheld and cherished business principles for which it
is widely recognized as a corporate entity committed to taking care
of the interest of all its stakeholders, abiding by the intrinsic values
of trust, integrity and excellence.
Tata Steel - Asia's first and India's largest integrated private sectorsteel company began with a modest capacity of two 200 - tons blast
furnaces, four 4 -tons steam-driven blooming mills and a rail and
structural mill. Today it stands as a state-of-the-art 3.5 million tons
steel plant capable of making the most rigorous demands of its
customers. Keeping abreast of the emergent technologies, Tata
Steel is now on the verge of becoming one of the most cost
competitive producers of steel. The 1.2 million tones Cold RollingMill, commissioned on April 24, 2000 has added value to Tata Steel's
present product mix, strengthen market leadership and penetrate
new markets.
With present capacity of 4.5 MT, It is looking forward to increasing its
capacity to 15 MT by 2010. Tata Steel produces longs as well as
Flats. Its latest acquisition of NAT STEEL produces long products that
have its global presence in 7 different countries.
-
7/30/2019 Cham Final
7/47
TATA Steel is one of the lowest cost steel producer as well as it is
supplier of high-end steel like supplied to auto OEM.
Tata Steel is one of the best-integrated steel plants and is having
facilities right from raw material production to finishing stage rolling.
Introduction to steel manufacturing:
Steel making is basically done in threestages:
1. Iron making process
2. Conversion to steel
3. Rolling Process
Steel is manufactured by injecting oxygen through liquid iron.
This is done in huge vessels known as LD (Linz Donnawitz)
vessel. In this process oxygen is passed at supersonic velocity.
The oxygen used is 99.5 % pure. This is done to reduce the
carbon content in iron to less than 2%. Flow dia. below
describes the steel manufacturing process at TATA Steel.
-
7/30/2019 Cham Final
8/47
COLD ROLLING MILL
IntroductionThe HR Coil coming from HSM is Cold Rolled because
1. Shape and Profile are better in CR as compared to HR.
2. Surface finish in HR Coil is not good.
3. Gauge accuracy of HR is not good.
The Cold Rolling Mill (CRM) ofTATA Steelis fully automated. The CRMuses Hot Rolled coil as its input and produces Cold Rolled galvanized
and Cold Rolled Annealed coils.
Reputed makers like Hitachi, Mitsubishi, IHI, LOI, CMI, ABB, SIEMENS etc
have supplied equipments.
Cold rolled steel sheets are produced by way of series of cold rollingprocesses, using hot rolled steel coils as the starting material. In the
cold strip mill, the scale on the hot rolled coils is removed by the
process called pickling (producing a product referred to as pickled coil).
The pickled coil is then cold rolled at room temperature to a thickness
of 0.15 to 3.2 mm. The cold rolling process is followed by the annealing
process and temper rolling. Compared to hot rolled sheets, cold rolled
sheets are thinner
Have superior thickness accuracy, and a smooth, attractive surface.
Cold rolled sheets are also superior in mechanical properties, especially
in workability.
These features mean that cold rolled sheets are suitable for
application which require small thickness of under 1.2 mm, which is
outside the conventional size range of hot rolled steels sheets, and
require not only stricter thickness accuracy but also an attractive
surface and excellent formability.
-
7/30/2019 Cham Final
9/47
Cold rolled steels sheets are also used as the substrate for various kinds
coated steels sheets such as zinc galvanized steel sheets, tin mill black
plates, and others
-
7/30/2019 Cham Final
10/47
-
7/30/2019 Cham Final
11/47
-
7/30/2019 Cham Final
12/47
Basics of CRM
1. The hot strip mill sends hot rolled coil (thickness 2 to 6 mm)
width (800-1500mm) to the CRM.
2. First the hot coil passes through the pickling section containingHCL acid in order to remove scales, making them ready for coldrolling.
3. Trimming section where the edges of the pickled hot rolled coilsare trimmed, if needed.
4. The coils are then fed into the main mill, viz. Tandem Cold Mill(TCM) (6 Hi, 5 stand mill). The CR strip thickness is 0.25 to 3.2mm. The strip thickness and shape is controlled within a verytight tolerance.
5. After cold rolling, the strip is either processed through annealing(BAF) + skin passing (SPM) or through any of the two galvanizinglines.
6. Part of coils which are sent through BAF + SPM, are firstprocessed in ECL.
7. About 2/3rd of CR goes to the Batch Annealing Furnaces (BAF)where the coil are stacked, covered and heated in closedatmosphere in a 100% hydrogen environment. This processimproves the mechanical properties of the strip and helps instress relieving. These coils are then processed through SkinPass Mill (SPM). Skin passing removes Luder bands, impartdesired surface finish, and improve flatness.
8. About 1/3rd of the production from PL-TCM goes to theGalvanizing Lines (CGL#1 & CGL#2), where the zinc coating isapplied on the strip by taking it through molten zinc bath. Thiszinc coating gives a sacrificial layer on the cold rolled strip forcorrosion protection.
9. Most of the coils are then taken through recoiling & Inspectionlines (RCL 1, 2 & 3) and are then packaged either manually orthrough coil packaging line.
-
7/30/2019 Cham Final
13/47
Pickling & Tandem Cold Mill (PLTCM)
Pickling is an important stage in the steel processing sequence. After hot
rolling and prior to cold rolling of strip. The aim of this operation is toeliminate oxide formed on the surface during hot rolling.
Pickling consist of treatment of the surface of the strip with
inorganic acid either hydrochloric or sulphuric. In order to improve the
efficiency of pickling it is preceded by mechanical de scaling (with help of
tension leveller) to crack and partially eliminate the oxides. The pickling
process then removes the remaining oxides and leaves a clean surface.
Pickling rate is faster with Hydrochloric Acid (HCL) then sulphuric acid.
Owing to enhancement of productivity along with other advantage we use
HCL acid as the pickling medium.
Various types of baths / tanks are used for pickling, for Tata steel CRM
shallow bath HCL continuous pickling has been chosen as the pickling
process.
Major purposes of pickling
To eliminate scales from hot rolled strip.
Improve cold rolling operatibility
-
7/30/2019 Cham Final
14/47
Ensure the appearance of strip
Improve the efficiency and quality of processes downstream, thesize of coil increased by welding.
A strip is trimmed on both the edges to a specified width.
Any portion of strip that are bound to be detrimental to downstreamprocesses or that to turn defective are eliminated
COLD ROLLING MILL
After the hot rolled coil surface is free from scale; it is rolled at room
temperature, referred to as cold rolling. For cold rolling mill complex it has
been decided to go in for a coupled pickling line (with shallow bath
pickling) and a 5-stand tandem mill (each 6-hi). This line has the capability
to produce strips with thickness accuracy better than +- 1%.
TANDEM COLD MILL
-
7/30/2019 Cham Final
15/47
Batch Annealing Furnace (BAF)
After cold rolling, annealing is done to soften the sheet for obtaining
superior mechanical properties for deep drawing application.
Annealing process restore ductility increases internal stresses and
restores formability of the cold rolled strips. Two widely different
annealing technologies are
a) Batch or box annealing Furnace (BAF)b) Continuous annealing
For aluminium killed low carbon steels, which form a major
portion of the product-mix, Batch Annealing has a distinct advantage
over continuous annealing.
For the Tata steels cold rolling complex, 100% batch annealing
has been chosen as the annealing route.
The batch annealing has following advantages.
a) Development of 100% h2 batch annealingb) Flexibility in input raw materialc) Process simplicityd) Economic lot sizee) Flexibility in capacity addition.
-
7/30/2019 Cham Final
16/47
Skin Pass Mill (SPM)
It is necessary to impart a small amount of deformation (typically
between 0.5 to 1.5%, depending on the grade) to annealed steel
strips for primarily
a) Preventing stretcher-strains mark during subsequent formingapplicationb) Imparting the desired surface texture (roughness) on the strip.
For CRM complex a skin pass mill of 1 mtpa capacity has been
selected having following facility.
a) 4 hi single stand mill with work roll bendingb) Wet type skin passing (using temper agent)
c) Work roll texturing using the Electrode Discharge texturing(EDT) method.
-
7/30/2019 Cham Final
17/47
Skin Pass Mill
Galvanizing Lines (CGL)
Galvanizing the coils protects steel sheets from corrosion attack by
acting as a barrier between steel and the environment.
Zinc and Zinc alloys have the ability to react at scratches and other
damages through an electrochemical (galvanic) action between
steel and zinc.
In the galvanic process zinc sacrifices itself to protect structural
integrity of the steel.
TWO LINES
1) One for construction( CGL # 1)2) One for auto/ white goods (CGL #2).
-
7/30/2019 Cham Final
18/47
CGL#1
BAF FLOW CHART:-
-
7/30/2019 Cham Final
19/47
STEPS INVOLVED IN BAF:
-
7/30/2019 Cham Final
20/47
1. Rolled steels are placed on the base and each rolled steels
are separated with the help of convector.
2. After that inner cover was placed on the rolled coils .3. N2 gas is passed through the inner cover to make the
atmosphere inert by the removal of air.
4. After that N2 gas was replaced by H2 gas.
5. When inner cover is filled with H2 gas then heating hood is
placed over the inner cover.6. After that the process of heating was done with the help of
COG, compressed air & spark.
7. When the heating was completed then the heating hood was
removed & apply cooling hood.
8. The process of cooling was performed with the help ofblower.
9. When the cooling is completed then cooling hood was
removed carefully with the help of crane.
10. Finally, inner cover was removed and the steel coils were
passed to CCSU.
-
7/30/2019 Cham Final
21/47
4. about industrial hydraulics:
Hydraulics is the transmission and control of forces and movements by
means of fluids. The fluids used to transmit the forces and movements aregenerally incompressible fluids, like water and oil. External forces applied
on it will increase the pressure of the fluid, which resist the external forces,
but the volume the fluid will remain constant. There are normally two
fields of application of hydraulics, which are completely distinct both in
their basic principles and in their potential application. When a load is
moved or hanged by the pressure energy of the system, as in a hydraulic
jack, it is called Hydrostatic power transmission, but, when high velocity
of fluid or very high kinetic energy of the fluid is used to get the high
rotation of a water turbine, it is called Hydrodynamic power transmission.
Industrial Hydraulics basically deals with the hydrostatic power
transmission.
Characteristic features of hydraulic systems:-
1. It is a self lubricated system.
2. Simplicity of operation.
3. Sensitive, smoothly variable speed controls.
4. The equipment is economical in space and weight.
5. Simple safe guarding against overloads, by means of a pressure limiting
valve.
6. Ease in monitoring and checking the hydraulic system by means of pr.
gauge.
7. Ease of transmitting motion and power from prime mover to machine.
8. As a gear box, it provides positive drive, hence no chances of slippage
between driver and driven elements.
-
7/30/2019 Cham Final
22/47
5. Project in BAF hydraulics:
SPECIFICATION OF CLAMPING CYLINDER:
There are 8 cylinders in BAF which are placed alternatively in the
base of furnace.
Four of them are non return valve (NRV) which holds the pressure.
Other four are non- non return valve (N-NRV) which does not hold
the pressure.
NRV have only inlet valve which allow the fluid to flow only in
single direction.
N-NRV has both inlet and exhaust valve which allow the fluid to
flow in both direction.
-
7/30/2019 Cham Final
23/47
6. HYDRAULIC CIRCUIT in baf :
-
7/30/2019 Cham Final
24/47
7. Procedure of cylindrical seal change:
7.1. Assembled required tools:
Assorted o rings picks
Socket wrench,1/2 drive
Piston ring compressor for 4bore
5/16allen wrench adapter for 1/2
Hone for 4 bore, 240 grit silicon carbide
3/16 Allen wrench
Ring removal pliers
Torque wrench, drive
Hydraulic fluid for seal lube (same as operating fluid)
-
7/30/2019 Cham Final
25/47
7.2. SEALS:-
ITEM 9A
ITEM 9B
ITEM 9C
TUBE SEAL o-
RING
ROD WIPER ROD SCRAPER
ITEM 9D ITEM 9E ITEM 9F
-
7/30/2019 Cham Final
26/47
ROD SEAL TUBE SEAL BACK-UP SPACEL SEAL
ITEM 9G
(MAGNET
RETAI)
7.3 COMPLETE CYLINDER DISASSEMBLY:-
Cylinder Prior to Disassembly:-
Secure the cylinder in a vise. For view of cylinder prior to
dissembled.
-
7/30/2019 Cham Final
27/47
Removal of the Flange Retaining
Screws:-
Extend the piston rod (Item 3) several
inches and inspect the rod end for burrs
and sharp edges. Remove any if present.
Use a socket wrench with a drive and
a 5/16 Allen wrench adapter to remove
the (8) screws
(Item 5)
Removal of the Flange:-
After removing the (8) flange retaining screws,
carefully slide the flange (Item12) off the rod.
-
7/30/2019 Cham Final
28/47
FLAN
GE (ITEM 12)
Removal of the Bushing Cartridge
After removing the flange, extend the piston rod several more inches.
Carefully slide the bushing cartridge (Item 10) off the rod.
Removal of the Rod Seal, Wiper and Scraper:
-
7/30/2019 Cham Final
29/47
After removing the bushing cartridge it is now possible to remove the
rod seal Item 9D), the wiper (Item 9B) and the scraper (Item 9C) from
the bushing cartridge. Be careful not to scratch the seal cavities. Use
a small, rounded edge screwdriver to aid in seal removal.
REMOVAL OF THE ROD SEAL,
WIPER AND SCRAPER
-
7/30/2019 Cham Final
30/47
Removal of the Transducer Cover:After the flange is removed, use a 3/16 Allen wrench to remove the (3)
transducer cover mounting screws (Item 16). Now, remove the transducer
cover (Item 15). See Figure 8.
3/16 Allen wrench
ITEM 16TRANSDUCER COVER
MOUNTING SCREW
FIGURE 8
REMOVAL OF TRANSDUCER
COVER
Removal of the Cap Retaining Screws
-
7/30/2019 Cham Final
31/47
After the transducer cover is removed, use a socket wrench with a drive
and a 5/16 Allen wrench adapter to remove the (8) cap retaining screws
(Item 6).
RETAINING SCREWS
Socket wrench, drive with
5/16 Allen wrench adapter
Removal of the CapAfter removing the (8) cap retaining screws, carefully remove the cap (Item
2).
Removing
the Tube Seal O-ring and the TubeSeal Back-Up:
-
7/30/2019 Cham Final
32/47
It is now possible to remove the tube seal o-ring (Item 9A) and the tube
seal back-up (Item 9E) from the cap (Item 2). Be careful not to scratch the
seal cavities. Use a small, rounded-edge screwdriver to aid in the o-ring
removal. See Figure 11.
ITEM 2
FIGURE 11
CAP REMOVING THE
TUBE SEAL O-RING AND TUBE SEAL
BACKUP
ITEM 9A ITEM 9E
TUBE SEAL O-RING TUBE SEAL BACKUP
Removal of the Piston/Rod Assembly:
-
7/30/2019 Cham Final
33/47
Place the cylinder in a vertical rod-up position. Pull the piston/rod
assembly (Item 3) out of the head/tube assembly (Item 1). Do not allow
the piston rod surface to contact the head/tube assembly during removal.
See Figure 12.
ITEM 1
TUBE
ITE
M 3
PISTON
REMOVAL OF THE PISTON RINGS:-
-
7/30/2019 Cham Final
34/47
To remove the (4) piston rings (Item 8) use ring removal pliers.
Inspect the piston and smooth any scratched surface using fine
grit emery cloth.
CLEANING THE HEAD/ TUBE ASSEMBLY:-
-
7/30/2019 Cham Final
35/47
Clean the inside of the head/tube assembly (Item 1) and inspect for
deep gouges and scratches. Light scratches and score marks can be
removed with honing or fine grit emery cloth. A heavily scored
surface required a new head/tube assembly.
7.4 CYLINDER REASSEMBLY:-
-
7/30/2019 Cham Final
36/47
INSTALLING THE PISTON RING:-
To install the (4) new piston rings (Item 8) fill the two centre
grooves on the piston first. Make sure splits are opposed.
REINSTALLING THE PISTON/ROD ASSEMBLY:-
After the (4) piston rings have been installed, place the
head/tube assembly in the vertical position. Lubricate the rings
and piston with system hydraulic fluid. Using a ring
compressing tool. Push the piston into the tube.
-
7/30/2019 Cham Final
37/47
REINSTALLING THE TUBE SEAL O-RING AND TUBE SEAL
BACK-UP:-
Clean all the tube seal o-ring (Item 9A) and tube seal back-up (Item
9E) cavities in the cap. Lubricate the tube seal and back-up with clean
system hydraulic fluid before installing into the cap. Use a small,
rounded- edge screwdriver to aid in reinstallation.
-
7/30/2019 Cham Final
38/47
REINSTALLING THE CAP:-After the tube seal o-ring and the tube seal back-up are installed in the
cap carefully place the cap(Item 2) onto the tub (Item 1) and tighten
the (8) cap retaining screws(Item 6) to 50 ft ibs using a torque wrenchwith drive and a 5/16 Allen wrench adapter. Always tighten
screws across each other rather than adjacent, to allow a more
uniform pressure on the tube seal o-ring.
-
7/30/2019 Cham Final
39/47
Reinstalling the Transducer Cover:After the cap (Item 2) is reinstalled, place the head/tube assembly in the
vertical position. Gently set the transducer cover (Item 15) onto the
head/tube assembly. Using a 3/16 Allen wrench, tighten the (3) transducer
cover mounting screws (Item 16).
ITEM 16
TRANSDUCER
COVERMOUNTING SCREW
ITEM 15
TRANSDUCER
COVER
3/16 Allen wrench
-
7/30/2019 Cham Final
40/47
ITEM 19
REINSTALLING THE
TRANS
DUCER COVER
Reinstalling the Rod Seal, Wiper and ScraperBefore reinstalling the bushing cartridge onto the
piston rod, reinstall the rod seal (Item 9D), the
wiper (Item 9B) and the scraper (Item 9C) into
the bushing cartridge (Item 10). Lubricate the
seals and seal cavities with clean system
hydraulic fluid. Use a small, rounded-edge
screwdriver to aid in seal installation. Be carefulnot to
scratch
the seal
cavities.
See
Figure
20.
ITEM 9D ITEM 9B ITEM9C
ROD SEAL ROD WIPER ROD SCRAPER
-
7/30/2019 Cham Final
41/47
FIGURE
20
ITEM 10
REINSTALLING THE ROD SEAL BUSHING CARTRIDGE
WIPER AND SCRAPER
Reinstalling the Bushing Cartridge:
After the rod seal, wiper and scraper have been installed into the bushingCartridge, lubricate the bushing cartridge with clean system hydraulic fluid
and carefully slide the bushing onto the piston rod.
REINSTALLING THE BUSHING CARTRIDGE
Reinstalling the flange:
-
7/30/2019 Cham Final
42/47
After the bushing cartridge has been installed, gently slide the flange
(Item12) onto the piston. Tighten the (8) flange retaining screws (item 5)
using a socket wrench with a drive and a 5/16 allen wrench adapter.
Always tighten screws across from each other, rather than adjacent. SeeFigure 22.
ITEM12 FIGURE 22
FLANGE REINSTALLING
THE FLANGE
Testing of the Reassembled Cylinder:Test assembled cylinder to 3,000 PSI minimum to check for external leaks.
To test for leakage past the piston rings, extend the cylinder to its full
extended stroke. Turn off the hydraulic system and release pressure.
Disconnect front port hose at supply end (leave connected to cylinder).
End of hose must be open to atmosphere (no quick coupler or quick
coupler with internal check).Place open end of hose in a container to catch
possible hydraulic fluid. Pressurize rear port so cylinder is at
full extension. Dead head at full pressure, check for fluid by
passing rings.
-
7/30/2019 Cham Final
43/47
8.INTERNAL DIAMETER OF CLAMPING
CYLINDER:-
-
7/30/2019 Cham Final
44/47
-
7/30/2019 Cham Final
45/47
9. Observation:-
-
7/30/2019 Cham Final
46/47
9.1 CAUSES OF HYDRAULIC SEAL FAIL IN CYLINDERS:-
Inexpensive Hydraulic Seal can cost us thousands in
downtime and loss of production if it fails.. If we have a
problem in seal, focus on these points to help
determine the cause of fail:-
Improper installation is a major cause of hydraulic seal failure.The important things to watch during seal installation are: (a)
cleanliness, (b) protecting the seal from nicks and cuts, and (c)
proper lubrication.
Other problem areas are over tightening of the seal gland wherethere is an adjustable gland follower or folding over a seal lip
during installation. Installing the seal upside down is a common
occurrence, too. The solution to these problems is common sense
and taking reasonable care during assembly
9.2 improvements:-
For improving the properties of seal and to prevent the seal failure we
have taken following actions:-
Earlier we are using the local seal (SPERAGE) which is
replaced by the new seals named INERPAC which has better
reliability and strength.
Insulation around the hydraulic cylinder has also prevented theseal failure to some extent.
-
7/30/2019 Cham Final
47/47
10. SOLUTION $ CONCLUSION:-
# It is not necessary to buy replacement seals from the hydrauliccylinder manufacturer. Many hydraulic seal suppliers have the same
exact seals that are used in most hydraulic cylinders and can easily
cross reference or match up a replacement. In many cases, if there is a
recurring problem with a seal, our seal specialist can recommend a
solution and increase the life of the seal.