case study wiendahl_2005

Upload: maheshvarpe

Post on 30-May-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 Case Study Wiendahl_2005

    1/18

    Production Planning & Control,Vol. 16, No. 7, October 2005, 634651

    Stumbling blocks of PPC: Towards the holistic

    configuration of PPC systems

    H.-H. WIENDAHL*y, G. VON CIEMINSKIz and H.-P. WIENDAHLz

    yInstitute of Manufacturing and Management (IFF),

    University of Stuttgart, Nobelstrasse 12, 70569 Stuttgart, Germany

    zInstitute of Production Systems and Logistics (IFA),

    University of Hannover, Scho nebecker Allee 2, 30823 Garbsen, Germany

    Manufacturing companies often complain about the difficulties they face in meeting theircustomers logistic requirements. Many blame the perceived inadequacies of their productionplanning and control (PPC) software for their performance deficits. The paper illustrateswhy this is only a partial view of the causes of the shortcomings. PPC software is just oneof six configuration aspects of the entire PPC system. The authors argue that the configurationof the PPC aspects objectives, processes, objects, functions, responsibilities and tools has to becarried out methodically and consistently in order for the PPC system to function properly.The analysis of examples of so-called stumbling blocks of PPC, inadequate configurationsof one or several of the aspects, supports this claim. The paper closes with the proposal of achecklist that the authors suggest as a first approach to ensure the consistent configuration ofPPC systems.

    Keywords: Production planning and control systems; Configuration aspects of PPC systems;Stumbling blocks; Configuration and operation of PPC systems; Actors in PPC

    1. Introduction

    It is almost 30 years since Orlicky (1975) first described

    the material requirements planning (MRP I) algorithm.

    To this day the algorithm remains the kernel of many

    production planning and control (PPC) systems. Despite

    30 years of progress in PPC theory and practice, and

    the definition of additional key functions, a large

    number of manufacturing companies remain unsatisfied

    with the degree of fulfilment of their logistic objectives.

    Recent surveys prove that companies still miss theirlogistic targets by a wide margin (Fraunhofer IPT

    Institute 2003, Wiendahl 2003a). This applies to the log-

    istic performance measures of productionwork-in-

    progress levels, throughput times and schedule

    reliabilityin the same way as to those of stores:

    inventory levels, service levels and delivery delays.

    A historical review reveals various causes of the

    unsatisfactory logistic performance and, considering

    these, the solutions that a holistic configuration of

    PPC systems requires. In the past, critical evaluations

    of PPC methods identified the limited capabilities of

    computer hardware as the principal cause for the insuffi-

    cient fulfilment of logistic objectives. These hardware

    limitations only allowed a step-by-step development

    of PPC algorithms. Due to this, the manufacturing

    resource planning (MRP II) algorithm that followed

    MRPI is characterised by the successive execution ofits functions. As real situations in manufacturing

    companies seldom conform to the rigid assumptions

    that are underlying this algorithm, there were calls for

    a more realistic consideration of practical conditions.

    PPC research therefore concentrated on the develop-

    ment of new functions and algorithms (Plossl 1985,

    Vollmann et al. 1997) and neglected the analysis of

    the required preconditions such as an organisational

    framework for PPC (Kraemmerand et al. 2003).*Corresponding author. Email: [email protected]

    Production Planning & ControlISSN 09537287 print/ISSN 13665871 online # 2005 Taylor & Francis

    http://www.tandf.co.uk/journals

    DOI: 10.1080/09537280500249280

  • 8/14/2019 Case Study Wiendahl_2005

    2/18

    Over time, the remarkable progress of computer tech-

    nology facilitated the application of more powerful

    planning software such as enterprise resource planning

    (ERP), supply chain management (SCM), advanced

    planning and scheduling (APS) or manufacturing execu-

    tion systems (MES) (Stadtler 2002). All of these systems

    carry out a considerably larger number of functionsthan their predecessors. They apply sophisticated

    mathematical algorithms to solve multi-variable

    optimisation problems and can thus consider numerous

    planning restrictions simultaneously. Due to the

    immense complexity of the implementation of these

    large systems they often fail to produce the substantial

    logistic performance improvements the companies

    are hoping for (Davenport 1998). In contrast, other

    businesses preferred simple PPC approaches. The

    increased popularity of just-in-time principles and

    Japanese management methods made companies avoid

    the application of software and focus on organisational

    aspects instead. They achieved remarkable performancegains, e.g. by the introduction of Kanban control cards

    (Soder 2004). The contrast between highly sophisticated,

    computerised PPC systems whose logistic performance

    is insufficient and simple, rules-based control mechan-

    isms that achieve astonishing results made researchers

    and industrialists realise that the problems of PPC

    cannot be solved by more powerful software alone.

    There seem to be other causes of the described perfor-

    mance deficits, which had been neglected so far.

    The standard textbooks on PPC offer detailed

    descriptions of the theoretical foundations of the PPC

    functions, mainly mathematical models and algorithms

    (Plossl 1985, Fogarty et al. 1991, Hopp and Spearman

    2000, Vollmann et al. 1997). However, instructions on

    the design and implementation of PPC systems are

    uncommon or not very detailed. Fogarty et al. (1991)

    emphasise that the choice of a logistic strategy should

    reflect the nature of the customer demands. The logistic

    strategy in turn determines appropriate manufacturing

    strategies and the corresponding feasible planning and

    control methods. Vollmann et al. (1997) stress the

    importance of mapping the planning and control

    processes specifically for the purpose of implementing

    PPC software to support the planning functions. The

    same authors provide a selection of the prerequisitesof the system implementation. Otherwise, there are

    only case studies on MRP or ERP system implementa-

    tions available that provide some indication on the

    critical success factors of PPC systems (see, for example,

    Akkermanns and van Helden 2002, Wiers 2002).

    In general management literature, important

    approaches are being discussed that aim to ensure the

    fulfilment of business objectives. Publications on PPC

    almost completely ignore these discussions, especially

    as far as the role of operational employees is concerned.

    Kaplan and Norton (1996) propose the balanced score-

    cards as a method to link business strategies to specific

    aspects of performance. Miles and Snow (1978) deter-

    mine what types of business organisations lead to

    above-average levels of performance. Maslow (1987)

    and Huczynski and Buchanan (1991) explain the impor-tant influence that human motivation and employee

    involvement have on the performance of a business.

    Storey and Sisson (1993) discuss the effects of

    performance-related pay on the performance of a com-

    pany and provide instructions on the effective design of

    remuneration systems. In order to ensure that PPC

    systems contribute to high levels of logistic performance,

    these general methods and approaches have to be

    adapted for the specific field of production management.

    Publications that transfer these approaches to the field

    of PPC have only recently been published (Wa fler 2003,

    Wiendahl and Westka mper 2004, Nyhuis 2004).

    According to the authors experience it is not only theneglect of above-mentioned important factors but also

    the lack of awareness of the correlations between sepa-

    rate factors that affect the configuration of PPC systems

    and lead to undesirable logistic performance deficits.

    These so-called stumbling blocks of PPC are errors in

    the configuration of a PPC system as a whole. The

    symptoms of these stumbling blocks, insufficient fulfil-

    ment of logistic objectives, a lack of transparency and

    excessive efforts required, are easily identifiable. Often

    though those responsible for PPC on the operational

    level are not able to simply remove the stumbling

    blocks. On the one hand the interdependencies between

    their causes make a final analysis more difficult; on the

    other hand, the changes required by the situation can

    exceed the competencies of the operational staff

    involved. In most cases, only the managing directors

    can remove the causes of the stumbling blocks.

    Therefore, the objective of this article is to create a

    framework for the identification, analysis and removal

    of classic stumbling blocks of PPC:

    . Section 2 defines the key terms of PPC. The PPC

    system, configuration aspects of PPC and

    stumbling blocks of PPC.

    .

    Section 3 describes typical stumbling blocks ofPPC. The descriptions first identify their respective

    symptoms, analyse their causes and present

    possible solutions to remove the stumbling blocks.

    The practical examples included in the discussion

    of each stumbling block are based on the experi-

    ences the authors gained in industrial projects.

    The projects focus on the configuration of PPC

    concepts, the selection of suitable software tools

    and the implementation of both in practice.

    Stumbling blocks of PPC 635

  • 8/14/2019 Case Study Wiendahl_2005

    3/18

    . Section 4 outlines a framework for the holistic

    configuration of a PPC system. It lays the founda-

    tions for a coherent and customised composition of

    the planning and control functions of manufactur-

    ing companies.

    . The conclusions in section 5 draw the insights

    together in the form of a questionnaire. The holisticconfiguration of a PPC system should consider the

    issues that the questionnaire raises in order to

    avoid the formation of stumbling blocks.

    This merges the aspects of the functions and data of

    PPC as well as its processes and responsibilities in an

    integrated model that provides a basis for the holistic

    configuration of PPC systems.

    2. Key terms of PPC

    The PPC system is the central logistic control mechan-ism that matches a companys output and logistic

    performance to the customer demands. The task of the

    PPC system is to plan, initiate and control the product

    delivery of a manufacturing company as well as to

    monitor and, in case of unforeseen deviations, i.e.

    disturbances or order changes, to re-adjust the order

    progress or the production plans.

    2.1 PPC system

    In the context of this paper, the term PPC system

    denotes the entirety of functions and tools used for the

    planning and control of the logistic processes in a

    manufacturing company. The scope of application of a

    PPC system includes the three value added processes,

    Source, Make and Deliver, in accordance to the termi-

    nology of the supply chain operations reference (SCOR)

    model (Supply Chain Council 2004) (cf. figure 1a). The

    input and output stores of a company are thus subject

    matter of a PPC system in the same way as production.

    The PPC system crosses company boundaries: It allowsfor the requirements of customers and suppliers since,

    following supply chain management principles, the

    management of the storage processes takes the delivery

    performance of the suppliers as well as the demand

    behaviour of the customers into account. According

    to this definition, the term PPC system comprises

    more than just the PPC software. The software is only

    the tool to plan and control the logistic process chain

    as well as the storage of production master data and

    feedback data.

    2.2 Configuration aspects of a PPC system

    On the basis of this definition, six configuration aspects

    of a PPC system can be distinguished (cf. figure 1b):

    . The logistic objectives of a company are situated

    at the heart of the PPC system. If necessary, these

    have to be differentiated for different departments

    of the company.

    . The PPC processes determine the logical and

    chronological order of PPC planning and control

    activities. Thus they define the workflow of order

    processing in terms of the information flow along

    the logistic process chain. The activities related to

    the material flow follow the same logic, but are not

    directly a subject matter of the PPC system.

    Value-adding processes

    Source Make Deliver

    (a) (b)

    Object Responsibility

    ProcessFunction

    Objective

    Figure 1. Definition of a production planning and control system. (a) Scope of application and (b) configuration aspects.

    636 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    4/18

    . The PPC objects are the planning objects of

    PPC. The most important objects are the articles

    (finished products, components or raw materials),

    resources (machinery and personnel) and orders

    (customer orders, spare parts orders, sample

    orders, etc.).

    . The PPC functions define the activities that arerequired to plan and control the logistic processes

    in the stores and in production. The fundamental

    activities are the definition of local objectives and

    targets, forecasting and decision-making, providing

    feedback on order progress as well as continuous

    improvement.

    . PPC responsibilities determine the positionsand

    therefore the members of staffthat are in charge

    of certain PPC activities. Conventional PPC

    systems ignore this organisational view as they

    operate on the assumption that responsibilities

    are organised by a central entity (see for example

    Hackstein 1989, Vollmann et al. 1997).. The five configuration aspects described above

    constitute the logical core of a PPC system. The

    purpose of the tools for planning and control is

    to support the operational order processing by

    (semi-)automated PPC activities. This creates stan-

    dards for the operational activities and relieves staff

    of time-consuming routine tasks. More time there-

    fore becomes available for the required planning

    and control decisions.

    These configuration aspects serve as a theoretical

    basis to analyse and remove the stumbling blocks

    of PPC.

    2.3 Stumbling blocks of PPC

    The presence of stumbling blocks of PPC becomes

    apparent through symptoms such as the insufficient

    fulfilment of logistic objectives, a lack of transparency

    of order processing or an unnecessarily high effort of the

    staff involved in carrying out PPC activities. The term

    stumbling block exclusively applies to internal mistakes

    in the configuration of the six aspects defined above.Factors related to the external environment such as

    unreliable suppliers or literally chaotic customers are

    not considered. The PPC system itself does not have

    any control over these factors. Nevertheless, the external

    factors represent requirements that have to be consid-

    ered when designing the PPC system.

    An analysis of the relationships between causes and

    effects is required in order to detect and remove the

    stumbling blocks.

    Ideally, the symptoms can be traced back to a single

    cause. In this case, only one configuration aspect is

    affected and the mistake in the configuration is easily

    detected and removed. An example is the entry of

    incorrect planned capacity values into PPC software.

    If, for instance, the capacity of a bottleneck work

    system has wrongly been set at 18 hours per workingday instead of the correct value of 16 hours, production

    overloads arise. This stumbling block can be

    easily removed by a simple correction of the planned

    capacity value.

    In cases where several cause-and-effect relationships

    influence or even amplify each other, the removal of

    stumbling blocks becomes more complex. Here, several

    of the configuration aspects are affected. Even though

    their symptoms are as apparent as for the simple

    stumbling blocks, their removal is a lot more difficult:

    It is necessary to, first, identify the relationships between

    the different causes. Secondly, the causes in different

    configuration aspects have to be changed simultaneouslyand in a co-ordinated way. Typically, this exceeds the

    competence of the operational actors so that their

    managers have to understand and remove the stumbling

    block.

    3. Typical stumbling blocks of PPC

    The following examples describe the stumbling blocks

    with several causes that are most commonly found in

    industrial practice. Each explanation is divided into the

    description of the symptoms and the analysis of their

    causes. Measures that are used for the removal of the

    stumbling blocks follow. The examples are based on real

    situations in industrial companies.

    3.1 Stumbling block missing positioning in system of

    logistic objectives

    The first example of a stumbling block of PPC highlights

    the importance of defining consistent objectives and of

    communicating the responsibilities for fulfilling the

    objectives clearly to the staff that plan production

    operations or carry them out.In PPC, one can often find conflicts between the

    logistic objectives work-in-progress level (WIP level),

    utilisation, throughput time and schedule reliability

    because they are neither compatible nor locally or

    temporally constant (Wiendahl 1995). Accordingly,

    one should never maximise or minimise the value of

    just one objective, but consider the simultaneous

    effects of measures on all logistic objectives. The nature

    of these conflicts has been recognised for some time

    Stumbling blocks of PPC 637

  • 8/14/2019 Case Study Wiendahl_2005

    5/18

    (Gutenberg 1951, Plossl 1991). Nevertheless, many com-

    panies are not aware of their consequences. Frequently,

    production managers are trying to optimise the utilisa-

    tion of work systems concurrently to the throughput

    time. Detailed investigations demonstrate that such an

    approach is not target-oriented because ultimately no

    single objective of the optimisation can be defined.Substituting the minimum-cost objective for the logistic

    objectives does not resolve the conflict. Instead, compa-

    nies should start by setting strategic objectives derived

    from the market environment (Ketokivi and Heikkila

    2003). Typical examples of such objectives are Reduce

    throughput times by 50% or Maintain a delivery relia-

    bility of 95%. These objectives serve as the priorities,

    which dominate the trade-off that has to be reached with

    the remaining logistic objectives. The production oper-

    ating curves are a proven methodology for the analysis

    of the interdependencies between logistic objectives and

    their consequences for PPC. They quantitatively

    describe the dependence of the objectives utilisation,throughput time and schedule reliability on the WIP

    levels in production and can easily be computed

    (Nyhuis and Wiendahl 2003). Figure 2 shows that the

    best possible target values for the different logistic objec-

    tives do not coincide at the same WIP level of a work

    system. A classical example of this phenomenon is the

    conflict between short order throughput times and

    high work system utilisation that was already

    mentioned. Whereas short work system throughput

    times can only be achieved at low WIP levels, high

    WIP levels are required in order to guarantee a high

    utilisation. This in turn leads to excessive throughput

    times. The situation requires a trade-off between

    the logistic objectives. Companies can achieve this by

    positioning their logistic processes at certain operating

    points on the production operating curves.

    The conflict between objectives described above

    only represents a stumbling block if those responsible

    ignore it in their day-to-day job. In a typical example,

    the managing directors of a medium-sized manu-

    facturer of construction components required shortthroughput times to achieve short delivery times.

    At the same time, they demanded a high utilisation

    of expensive machinery in order to obtain a fast

    return on investment. The production operation curves

    clarify the conflict that the production department

    faced as a result (cf. figure 2): On the one hand,

    the objective of short throughput times requires a

    low WIP level in production (WIPTTPmin). On the

    other hand the objective of a high utilization

    necessitates a high WIP level (WIPUmax). The inconsis-

    tent directives of the directors are the cause for two

    stumbling blocks:

    . In day-to-day business, concrete decisions concern-

    ing orders have to be taken. Conflicting manage-

    ment directives fail to determine the most

    important logistic objective. As a result a guideline

    for these decisions is missing.

    . As the management directives described above are

    contradicting in themselves the target values that

    are derived from them have to be as well.

    Therefore it is impossible for operational planners

    to take rational decisions.

    The production operating curves are helpful tools to

    analyse and remove both stumbling blocks:

    . Initially, the curves explain the interdependencies

    between the logistic objectives and facilitate their

    relative prioritisation (step 1 of the logistic posi-

    tioning).

    . The remaining target values follow from the value

    set for the most important objective. For example,

    the desired throughput time determines both the

    target utilisation as well as the target WIP level

    (step 2 of the logistic positioning).

    Taking a strategic decision, the directors regarded

    short throughput times as the most important objec-

    tive. However, in order to implement the new manage-ment directives, further boundary conditions had to be

    considered. The machine operators still tried to

    maintain high WIP levels at the work systems so

    that they always see a work load in front of their

    machines and can reduce setup times by changing the

    sequence of orders. Obviously, this strategy also

    supports a high work system utilisation. At the same

    time it adversely affects throughput time and schedule

    reliability.

    WIP level

    Utilisation

    Maximum

    SchedulereliabilityMaximum

    Minimum

    Throug

    hputtim

    e

    WIPUmaxWIPTTPmin0

    WIPTTPmin: WIP level at targetthroughput time

    WIPUmax : WIP level attarget utilisation

    Figure 2. Logistic operating curves as a model of theinterdependencies between logistic performance measures.

    638 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    6/18

    In order to maintain the desired prioritisation of the

    logistic objectives, management should take the follow-

    ing actions:

    . Offer qualification in production logistics to all

    relevant employees (including shop floor operators)

    and communicate the new priorities of the logistic

    objectives.

    . Verify the conformance of the logistic objectives

    with the interests of the employees. In particular,

    management has to ensure that compensation

    schemes effectively support the objective of short

    throughput times.

    The following section describes how those involved

    influence production planning and control, and

    how their decisions impact on the fulfilment of logistic

    objectives.

    3.2 Stumbling block divergent stakeholder interests

    The second stumbling block confirms the importance of

    the consistency between the logistic objectives and the

    PPC staff who have the responsibility for meeting the

    targets. It also stresses the fact that staff has to be

    qualified in order to carry out PPC functions.

    In an empirical study on the implementation of ERP

    systems, Amoako-Gyampah (2004) came to the conclu-

    sion that different levels of the management hierarchy

    have different perceptions of the system to be intro-

    duced. It is therefore essential that the managing

    directors not only provide all future users with adequate

    training in the application of the new system, but that

    it is equally important they make efforts to convince

    staff members of the benefits of the change and of the

    necessity to utilise the new system to achieve enhanced

    business objectives.

    The report by Wiendahl et al. (2002, 2005) on the

    introduction of a Kanban control is a prominent exam-

    ple for the potential for conflicts between such business

    objectives and the individual objectives and interests of

    production employees. In this case, production manage-

    ment wanted to reduce throughput time and WIP levels

    significantly. The central planning department wasresponsible for the design of the Kanban system and

    the setting of its parameters. On the basis of customer

    demands and target replenishment times the planners

    also calculated the number of Kanban cards required.

    The production department was briefed about the

    changes and a subsequent trial run passed without

    problems. The company therefore regarded the

    implementation of the new production control system

    as a success.

    It came as a surprise that the production was not able

    to sustain the aspired improvements for more than a

    short time after implementation of the new control

    system. Rather, both the values of WIP and throughput

    times soon rose to old levels again. The detailed analysis

    of the production department that was initiated as a

    consequence, revealed insufficient consultation with theproduction operators.

    The operators pursued the objectives job security

    and stable order processing by stockpiling orders for

    uncertain times in the future. This leads to unnecessary

    safety stocks, permanent changes to the order sequence

    and decreasing schedule reliability.

    Obviously the pull principle that is underlying the

    Kanban control does not conform to these interests of

    the production operators: Kanban enforces temporary

    idle times for most work systems. In order to counteract

    this, the operators added copied Kanban cards to the

    Kanban control loops to raise WIP to the previous

    levels. Thus, they apparently resolved the conflictsbetween the objectives of the company and their own

    individual objectives. Production management only

    realised that the unwanted modifications had been

    made and understood the exact causes of the modifica-

    tions after the analysis of the Kanban control system.

    The example highlights the prerequisites for a

    sustained successful implementation of the new control

    system; thorough qualification of all staff involved and

    an incentive system that emphasises the objectives of

    due-date oriented order processing (in order to avoid

    order sequence modifications) and flexible working

    hours (in order to guarantee processing on demand)

    rather than promoting the conventional objective of

    high resource utilisation.

    3.3 Stumbling block missing responsibility

    for inventories

    The third stumbling block illustrates the consequences

    of a lack of coordination of the responsibilities for the

    PPC processes and objects. They result in an insufficient

    fulfilment of the logistic objectives.

    Often, there is no clear dividing line separating onearea of responsibility from another. Typical symptoms

    are high inventory levels of purchased components and

    finished products, or recurrent discussions on the

    binding effect of orders and their reliable fulfilment.

    The company described in this section produces

    make-to-order machines of medium complexity. Depen-

    ding on the customer requirements, this may include

    engineer-to-order operations. A detailed analysis

    was initiated by the managing directors who were

    Stumbling blocks of PPC 639

  • 8/14/2019 Case Study Wiendahl_2005

    7/18

    dissatisfied with the high inventory levels of purchased

    components and finished products, and the uncertainties

    caused by sudden changes of due-dates or engineering

    changes.

    Figure 3a shows parts of the order processing chain.

    Figure 3b indicates the problems resulting from an

    unclear definition of interfaces: The production isresponsible for the material flow from the start of the

    production order (i.e. printing of order documentation)

    to the final operation (i.e. input to store). This includes

    the responsibility for throughput times and WIP

    levels. Subsequently, the finished products are handed

    over to the sales department, either to be delivered

    immediately or to be stored in the finished product

    store. The purchasing department has the responsibility

    for all purchased components. However, there is no

    responsibility defined for the target inventory levels for

    finished products. The company neither deemed it neces-

    sary to define nor to regularly monitor them, because

    final assembly should not take place before there is acustomer order. This should have prevented finished

    products from being stored.

    Recurring appeals to cut inventory levels remained

    without effect. Instead, purchased component and

    finished product inventory levels were steadily growing.

    In addition, staff in the shipment area complained about

    too small dispatch and storage spaces. The root cause

    analysis showed:

    . Initially, customers insist on the machines being

    delivered as soon as possible. Near completion of

    the order, they tend to postpone the delivery date

    when they realise that the machine is not needednow, e.g. because of building delays.

    . The actual start date of production is delayed

    relative to the planned start date. The reasons are

    product engineering changes due to changes in

    customers requests or design modifications by the

    engineering department.

    Two issues have to be solved to improve the

    interfaces:

    1. Placing of orders (information flow): Does the

    person who acquires new or altered information

    directly benefit or have a quantifiable advantage

    from passing it on? Would it be to his/her

    disadvantage if he/she did not pass it on?

    2. Delivery of orders (material flow): Does the

    supplier have a direct, quantifiable benefit from a

    timely delivery to his/her successor? Would a late

    delivery be to his/her disadvantage?

    In our example, a handover deadline was fixed for the

    transfer of products to the shipment area, which iswithin the responsibility of the sales department. The

    resulting deadlines are realistic, because the calculation

    of the order flow includes a capacity check.

    . From a production point of view, the sales depart-

    ment places fixed orders. The fact that products

    are handed over without transferring inventory

    responsibility to the sales department is the reason

    why the sales department experiences neither an

    advantage nor any disadvantage if it fails to pass

    on the postponement of customer due dates.

    . Likewise, from a sales point of view, the promise

    made by production seems to be binding. Butproduction has no fulfilment risk: delivering

    Throughput time production order Idle time Idle time

    Finishedproducts

    ... ...

    Parts fabrication order I

    Assembly order

    OP 4

    Time

    Printing order documentation Input to store

    OP 1

    Shipment

    Parts fabrication order II

    Responsibility Production

    Start-up

    ResponsibilityPurchasing

    Purchasing

    ResponsibilitySales

    (a)

    (b)

    Purchasedcomponents

    Purchasing Production Sales

    placesfixed order

    deliverson time

    placesfixed order

    deliverson time

    Figure 3. Stumbling block missing responsibility for inventories. (a) Status as planned and (b) actual status.

    640 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    8/18

    goods on time means production is cleared of its

    responsibility, without having to worry about

    any penalties when orders are completed behind

    schedule.

    A possible solution may be to add the finished

    product store to productions responsibility. This initi-

    ates the necessary improvements out of self-interest.

    An analysis of the interface between production

    and purchasing shows similar results: The required due

    date for purchased components is calculated by back-

    ward scheduling, before passing it on to the suppliers

    with a safety lead time. Production takes no responsi-

    bility for inventory levels from the planned start but

    only after the order is actually started. This is why

    production is merely interested in passing on informa-

    tion regarding production orders being pulled ahead

    but not about orders postponed. Frequently, the pro-

    blem is solved by transferring the responsibility for

    material dispatch and material inventory responsibilityto production.

    3.4 Stumbling block inconsistent responsibilities

    for functions

    If the responsibilities for PPC objects, functions and

    objectives are defined inconsistently, top management

    is obliged to spend a high effort on resolving unneces-

    sary disputes as the following example exemplifies.

    One of the principal tasks of management is to clearly

    define the responsibilities and assign the functions

    within a company. It is generally accepted that appro-

    priate objectives have to be defined so that responsibil-

    ities within the organisation are consistent and therefore

    the functions be carried out reliably (Kaplan and

    Norton 1996). Unfortunately, reality often rather

    reflects the informal organisation, i.e. the power struc-

    ture among the persons concerned.

    In a company with 300 employees, the right way to

    fulfil functions and to accomplish the given objectives

    was the subject of heated discussions among the three

    departments of dispatch, production and logistics:

    Dispatch is responsible for order release, productiontakes on capacity control and sequencing at the

    work systems, and logistics is responsible for promising

    delivery dates, thus being partially in charge of order

    generation. Each department has its own system of

    objectives, the priorities differ: The primary objective

    of dispatch are short throughput times, the principal

    goal of production is a high utilisation, while the top

    priority of logistics is a high schedule reliability.

    All these objectives were quantified by targets. The

    resulting conflicts are illustrated by the following

    disputes:

    . Dispatch aims to release orders at the latest

    possible moment to meet the objective of short

    throughput times. Whenever demand is low,

    intense debates with production are unavoidable.Production wants orders to be released much

    earlier to maintain a high utilisation.

    . To meet the objective of high schedule reliability

    and ensure that customers receive their products

    on time, logistics strives for realistic delivery

    promises. It sets the planned start and finish dates

    as well as the sequence of orders in accordance with

    these promises. As soon as demand rises, however,

    the available capacities are not sufficient to keep the

    promised delivery dates. Hence, production is

    urged to raise capacity. If this is not possible, the

    dispatch department is asked to release orders at

    an earlier point in time.. Usually, the parties concerned are not able to reach

    an agreement. Therefore, often top management is

    asked to solve the conflict and decide upon which

    orders to release or which to speed up. Necessarily,

    the set objectives are missed.

    A helpful framework to remove this stumbling

    block is Lo ddings (2004) model of manufacturing

    control. Its basic idea is to combine the functions of

    manufacturing control with the objectives of the

    PPC system. Thus, it becomes possible to assess whether

    the responsibilities for functions and objectives are

    consistently defined. He defines the following fourfunctions (cf. figure 4a):

    . Order generation determines the planned input and

    output, as well as the planned order sequence.

    . Order release determines when orders are released

    to the shop floor (actual input).

    . Capacity control determines the available capacity

    in terms of working time and the number of staff

    assigned to work systems, and thus affects the

    actual output.

    . Sequencing determines the actual sequence of order

    processing for a specific work system, and thus

    affects schedule reliability.These functions affect the three manipulated variables

    input, output and order sequence. The discrepancies

    between two manipulated variables lead to the observed

    variables of manufacturing control (cf. figure 4b):

    . The start deviation results from the difference

    between planned input and actual input.

    . The WIP level results from the difference between

    actual input and actual output.

    Stumbling blocks of PPC 641

  • 8/14/2019 Case Study Wiendahl_2005

    9/18

    . The backlog results from the difference between

    planned output and actual output.

    . The sequence deviation results from the discre-

    pancy between actual and planned sequence.

    The observed variables affect the objectives of PPC

    described above, i.e. throughput time, WIP level,

    utilisation and schedule reliability.

    Figure 4b shows the interdependencies connecting

    functions, manipulated variables, observed variables

    and objectives to each other. The functions define the

    manipulated variables, the observed variables resultfrom the discrepancies between two manipulated

    variables, and the logistic objectives are determined by

    the observed variables.

    As a basic principle, conflicts arise when one de-

    partment takes the responsibility for a specific ob-

    jective when the accomplishment of this objective is

    also affected by another department. These conflicts

    obviously cannot be resolved by the persons involved.

    Figure 5 illustrates how the responsibilities for

    objectives and functions are defined by the described

    company:

    .

    The first conflict arises between the production andthe dispatch departments: Although order release

    (via actual input) and capacity control (via actual

    output) affect the objectives of throughput time

    and utilisation, the responsibility for objectives

    and functions is not united under one authority.

    Accordingly, situations, in which the achievement

    of an objective depends on the decisions of the

    other department, require a higher authority to

    make the final decision.

    . The second conflict arises between the production

    and the logistics departments: Production affects

    the objective of schedule reliability via capacity

    control (actual output) and sequencing, whereas

    logistics impacts the objective via order generation.

    Again the responsibility for objectives and func-

    tions is not united under one authority. This inevi-

    tably leads to a permanent conflict as described

    in the above paragraph and requires a higher

    authority to solve each case. For production to

    call for an earlier order release to ensure utilisation

    even complicates the matter, as a third party, i.e.

    dispatch, has to be considered.

    To remove this stumbling block the responsibility for

    the complete order processing chain must be put into

    the same pair of hands. An order management centre

    could fulfil this role. Alternatively, it is possible to

    divide the order processing chain into sub chains, in

    which the responsibilities for objectives and functions

    are combined.

    3.5 Stumbling block insufficient quality of feedback data

    The insufficient quality of feedback data reported in

    the following case is a symptom of the lack of

    integration of all PPC functions in the tools for planning

    and control.

    Data quality has recently been identified as one of the

    important factors in the configuration of PPC system

    (Xu et al. 2002). All purposeful and successful planning

    2

    13

    4

    Ordergeneration

    Orderrelease

    Capacitycontrol

    Sequencing

    Production

    (a) (b)

    Disposition

    Ordergeneration

    Plannedinput

    Plannedoutput Backlog

    Schedule reliability

    Utilization

    WIP level

    Throughput time

    Startdeviation

    ActualInput

    WIPlevel

    Actualoutput

    Capacitycontrol

    Orderrelease

    Plannedsequence

    Sequencedeviation

    Actualsequence Sequencing

    Observed variable

    ObjectiveDirection

    Manipulated variableFunction

    Difference

    Figure 4. Model of (a) functions and (b) logistic interdependencies in manufacturing control. Adapted from Lo dding (2004).

    642 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    10/18

    and control depends on a complete, consistent and

    current data basis for all planning, control, execution

    and performance measurement activities (Wiendahl

    et al. 2003a). Besides the production master data, the

    production feedback data are especially important for

    this purpose:

    . Feedback data represent the inputs for the logistic

    performance measurement carried out at the end ofa production planning period. Deviations between

    the planned and actual values of logistic perfor-

    mance measures lead to new control decisions or

    the adjustment of target values (see section 3.6).

    . For day-to-day business the continuous logistic

    performance monitoring is more important.

    The deviations between planned and actual order

    progress detected by this function have to be

    corrected by immediate control measures in order

    to make sure that promised or planned due-dates

    can be maintained despite order changes or

    inevitable disturbances.

    There is a range of possible causes for the insufficient

    quality of feedback data, of which the IT structure in a

    manufacturing company is one of the more significant

    reasons. In a survey carried out by the Fraunhofer

    Institute for Systems and Innovation Research in 2001,

    60% of the companies responded that there is no

    hardware connection between the production data

    acquisition (PDA) software and the remaining IT

    structure (Beckert and Hudetz 2002). A timely and fast

    intervention of production control in production is thus

    impossible.

    At times there is a complex structure of mutual

    dependencies that is underlying the symptoms. This is

    exemplified by the following example: In the manufac-

    turing company considered, the feedback data were

    characterised by inconsistencies that resulted from a

    substantial delay in recording the data in the PDA

    software (only 75% of operations showed a positivethroughput time). However, the actual processing

    times matched the standard processing times relatively

    accurately. After the introduction of new planning

    software the problem disappeared within a period of

    six weeks.

    A preliminary analysis showed that the feedback data

    were only used for the controlling of costs but not for

    the ongoing monitoring of the order progress. A second

    manual feedback systemlocal inspections by the

    foremenprovided the feedback information required

    to control the order progress in time. As the feedback

    data were not immediately incorporated in the nextproduction plan, the operators did not recognise the

    benefit of the plausible and immediate provision of

    feedback data. The regular appeals by the production

    managers to increase the quality of the feedback data

    therefore did not have any effect.

    The PPC cycle shown in figure 6 provides a basis for a

    detailed analysis of the situation. It consists of a logical

    sequence of the activities of production planning and

    control. Based on insights from decision theory, the

    LogisticsOrder

    generation*

    Dispath

    Production

    Throughput time

    Utilization

    Plannedoutput

    Backlog Actualoutput

    WIP level

    Actualinput

    Orderrelease

    Dispatch

    Capacitycontrol

    Production

    Sequencing

    * promised delivery date

    Actualsequence

    Sequencedeviation

    Plannedsequence

    Logistics Schedule reliability

    Function

    Difference

    Objective

    Direction

    Observed variable

    Manipulated variable

    Responsibility

    Stumbling block

    Figure 5. Stumbling block inconsistent responsibilities for functions.

    Stumbling blocks of PPC 643

  • 8/14/2019 Case Study Wiendahl_2005

    11/18

  • 8/14/2019 Case Study Wiendahl_2005

    12/18

    requirements planning and one for the capacity require-

    ments planning and scheduling. Therefore there are two

    relevant types of stumbling blocks:

    1. Inconsistent parameters: The scheduling parameters

    at different levels of aggregation are inconsistent

    (e.g. the offset of a manufactured component is

    equal to 3 weeks, the sum of the throughput times

    of all operations included in the manufacturing

    order is equal to 4 weeks).

    2. Unrealistic parameters: The values of the schedul-ing parameters are normally not maintained at the

    planned values in reality (e.g. the mean planned

    throughout time of manufacturing orders is equal

    to 5 days whereas the actual mean throughput time

    is equal to 7 days).

    Manufacturing companies often underestimate the

    significance of correct parameter setting. The scheduling

    parameters are merely estimated or derived from

    historic data. In this way, a tool manufacturer used a

    mean planned throughput time value of 27 working days

    for scheduling manufacturing orders. This value was

    based on the experience of the production foreman.The actual mean value of the throughput time for the

    manufacturing orders was equal to 32.5 working days.

    The differences between plan and actual mean values

    occurred due to the production bottleneck: a long

    operation throughput time of a coating process.

    The prerequisite for realistic planned values is

    the knowledge of the actual values. The lack of a

    performance monitoring function constitutes an obvious

    stumbling block in this context. The company consid-

    ered did lack this function:

    . The feedback dataorder master data and due

    dateshave to be recorded at all work systems

    on the shop floor (step Collect in the PPC cycle

    in figure 6). Subsequently, order throughput times

    and other logistic performance measures can be

    calculated from these.

    . Subsequently, logistic performance measurement

    has to determine the accuracy of the planningparameters. This is achieved by comparing the

    throughput time parameters set for the scheduling

    function of the PPC software with the actual values

    measured in production. If necessary, the param-

    eters have to be adjusted bearing in mind the

    logistic objectives (step Learn in the PPC cycle

    in figure 6).

    . Only the introduction and regular execution of

    the PPC cycle guarantees the accuracy of the

    throughput time parameters. The procedure

    described equally applies to all other PPC planning

    parameters.

    Adjusting parameters may lead to another stumbling

    block: For the purpose of replenishing the finished

    products store, the order dispatch function assumed a

    throughput time of 27 working days. Backward sched-

    uling runs generated the required production orders

    based on this assumption. Thus, the difference of

    5.5 days between the planned and the actual

    throughput time affected the schedule reliability. The

    OPOP

    Dispatch level123

    IA

    B

    1

    2

    3

    1 3

    Throughput time operation 2

    OP2

    B

    Throughput time production order B

    Offset dispatch level 2Time

    Time

    Time

    Material requirementsplanning:BOM explosion and

    offsetting

    Capacity requirementsplanning:throughput scheduling

    Function Parameter

    Replenishment time/offset dispatch level

    Planned orderthroughput time

    Planned operationthroughput time

    Aggregation level

    Product (mean) purchasing time of entirepurchasing process (external/internal)

    Dispatch level (BOM level)

    may include one or moreproduction orders

    Production order (mean) throughput time ofproduction order

    equal to replenishment time ifdispatch level includes only oneproduction order

    Operation (mean) throughput time of operationof production order

    estimated or calculated(inter-operation time + operation time)

    Figure 7. Classical scheduling parameters of PPC.

    Stumbling blocks of PPC 645

  • 8/14/2019 Case Study Wiendahl_2005

    13/18

    production was running into backlog. For this reason,

    companies have to be aware not to enter the

    vicious circle of production control when modifying

    planning parameters. The next section explains

    how to act correctly when these modifications become

    necessary.

    3.7 Stumbling block lack of logistic understanding

    Due to a lack of logistic understanding, many manufac-

    turing companies fail to make the correct connections

    between decisions taken in the PPC functions and

    their effect on the degree of fulfilment of the logistic

    objectives.

    How a production system deals with logistic issues

    and how this affects planning and control has been the

    subject of discussion for some time, especially in view

    of the familiar shortcomings of the MRP approach andthe lack of logistic understanding on the part of the

    users of PPC.

    The vicious circle of production control is a particu-

    larly illustrative example of how little is known about

    the actual interdependencies between manipulated and

    observed variables (cf. figure 8). In the USA this circle

    was first described by Mather and Plossl (1978), while

    Kettner (1981) and Wiendahl (1995) explained its

    consequences to the German audience. The vicious circle

    sets out from the mistaken conclusion that schedule

    reliability is poor because the planned throughput

    times are too short. This is shown in the throughput

    diagram in figure 9a. When increasing the values of

    the parameters in the backward scheduling run, the

    orders will be released to the shop floor much earlier.

    As orders cannot be started in the past, the input curve

    takes a leap (one-off load surge), making the WIP levels

    at the work systems and hence the length of the orderqueues grow (cf. figure 9b). This implies, on average,

    longer waiting times and longer throughput times of

    orders, along with an increased variation of throughput

    times (Wiendahl 2002).

    As a result, the schedule reliability is decreasing

    and completing important orders on time is only

    possible by means of rush orders and costly expediting

    exercises. The vicious circle is spiralling upward to

    stabilise at a level where the amount of work pieces

    stored as work-in-progress exceeds the storage capacity

    (Wiendahl 1995).

    The correct logistic analysis would be as follows: The

    backlog is the actual cause of the due-date deviation of

    orders (cf. figure 10a). This backlog cannot be reduced

    by increasing the planned throughput times, but by

    temporarily increasing capacities or outsourcing work.

    Figure 10b shows the effects of this intervention: From

    the present day the backlog will gradually decrease.

    As a result, adherence to the planned due dates is

    improving, and from a certain point in time planned

    and actual output are matched. However, such reactions

    call for flexible capacities (Wiendahl 2002).

    Outsourcing work for some time basically has the

    same effect. However, compared to an increase of

    capacity the impact will be delayed (cf. figure 10c).

    Throughout

    times and their

    variation

    increase

    Length of

    queues

    increasesPlanned

    throughput

    times are

    increased

    Load on

    work systems

    increases

    Orders

    are released

    earlier

    Insufficient

    delivery

    reliability

    Figure 8. Stumbling block lack of logistic understandingcauses vicious circle of PPC. Adapted from Plossl and Kettner.

    Present day

    Actual output

    Input

    (planned/actual)Planned

    output

    TimePresent day

    Time

    Planned

    output

    New planned

    throughput time

    (a)

    (b)

    Load

    surge

    Planned input

    = Actual input

    Due-date deviation

    (too late)

    Planned

    throughput time

    Planned

    throughput time

    New actual

    throughput time

    Due-date deviation

    (too late)Actual

    output

    Workcontent

    Workcontent

    Actual

    throughput time

    Figure 9. Inadequate logistic reaction to interrupt viciouscircle of PPC. Throughput diagrams for (a) initial situationand (b) for an increase in planned throughput times.

    646 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    14/18

    A similar effect may be achieved by deferring make-to-stock orders (orders not related to a customer request)

    or rejecting customer orders, though the latter might

    have a negative effect on the market.

    3.8 Stumbling block inadequate logistic guidelines

    The stumbling block described below shows the

    consequences of a lack of consistency between the

    PPC functions and the process, which the functions

    are meant to control.

    An important instance of wrong PPC parametersetting is the formulation of inadequate logistic guide-

    lines. In this case, the planned throughput times entered

    in the PPC software are realistic and match the mean

    value of the production throughput times. However,

    the variation of the actual throughput times is higher

    than the planned tolerance. Hence, the available

    planning functionality (throughput time planning

    based on mean values) and the actual throughput

    time performance (high variation of throughput times)

    do not conform. This inconsistency shows analogies to

    fluid mechanics (Wiendahl 2003b):

    . Throughput time planning based on mean values

    assumes that the order stream resembles a steadily

    flowing river (a so-called laminar flow of orders).

    Only when throughput time variation is very low,

    schedule reliability is sufficient.

    . If the order stream resembles a mountain torrent

    (comparable to a turbulent flow of orders),

    the focus has to be on the individual order. The

    individual planning of throughput time ensures

    schedule reliability despite strongly varying

    throughput times.

    Such a situation allows for two alternatives:

    . On the one hand, logistic turbulences might

    be inevitable. Individual throughput times are

    necessary and the software must be adapted

    accordingly.. On the other hand, the steady-river scenario is

    feasible. Orders are processed according to the

    FIFO rule (or maximum slack). A low variation

    of throughput times ensures the planned schedule

    reliability.

    The relationship between logistic requirements

    and logistic capabilities determines the choice of a

    logistic guideline. The requirements depend on the

    allowed due-date deviation (tolerance requirements),

    the demand fluctuation (flexibility requirements) and

    the delivery time (speed requirements), cf. figure 11

    (Wiendahl et al. 2002, 2003b):

    . Tolerance requirements: Is the planning tolerance

    set for a value such as throughput time, smaller

    than the actual variation?

    . Flexibility requirements: Do the fluctuations in

    demand exceed capacity flexibility?

    . Speed requirements: Do heterogeneous delivery

    times require heterogeneous throughput times?

    If the requirements exceed the capabilities, it is

    necessary to apply individual throughput times for

    each order. Practical experience shows that missing one

    of the three requirements is sufficient to increase the var-

    iation of throughput times. In most cases, this is due

    to varying order priorities or sequence changes meant

    to avoid setup times. Accordingly, sufficient planning

    tolerances, little demand fluctuations and homogeneous

    delivery times allow for order throughput times to be

    based on mean values. The same applies vice versa:

    Heterogeneous delivery times, considerable fluctuations

    in demand and tight planning tolerances call for the

    individual planning and control of orders.

    Planned input= Actual input

    Planned Input= Actual input

    Present day

    Present day

    Time

    Time

    Actual output

    Backlog

    Planned output= Actual output

    Planned output

    Backlog

    (b)

    (a)

    TimePresent day

    Outsourcing

    (c)

    Planned input= Actual input

    Planned output= Actual output

    Workcontent

    Workcontent

    Workcontent

    Backlog

    Figure 10. Adequate logistic reactions to interrupt viciouscircle of PPC. (a) Initial situation, (b) temporary increase incapacity and (c) temporary outsourcing.

    Stumbling blocks of PPC 647

  • 8/14/2019 Case Study Wiendahl_2005

    15/18

    Following a flow-oriented guideline makes it easier to

    forecast the throughput time and thus to determine the

    delivery date. Traditional PPC methods support this

    approach, too. However, strong fluctuations in demand

    and unforeseen events make it difficult to providecapacity according to need. This is why it places high

    demands on flexible capacities and predictive perfor-

    mance monitoring to achieve the ideal of a steady

    order stream.

    4. Configuration of the production planning

    and control system

    Many industrial companies are dissatisfied with the

    degree to which they fulfil their logistic objectives:

    throughput times and inventory levels seem to varyuncontrollably; promised due-dates can only be adhered

    to by use of costly expediting exercises. For this reason,

    there are controversial views about the potential of PPC

    software in academia and practice.

    The examples of stumbling blocks of PPC presented

    above show that the ever-present demand for improved

    software with more powerful algorithms is not always

    justifiable. Rather, it is the inconsistent configuration

    of the aspects of PPC that affects the fulfilment of

    logistic objectives. A holistic (re-)configuration of the

    PPC system has to consist of the following three stages:

    . Initially management has to determine the logistic

    strategy, i.e. the logistic performance that it wants

    to offer to the customers. This includes the prior-

    itisation of external logistic objectives and the

    trade-off between internal logistic target values.

    Manufacturing companies have to ensure that the

    logistic strategy matches their manufacturing vision

    which predetermines the design of its production

    systems (Riise and Johansen 2003). In fact, compa-

    nies should ideally formulate manufacturing and

    logistic strategies simultaneously and also design

    production systems and the related PPC system in

    parallel.

    . The technical concept of the PPC system has to be

    built on the basis of the logistic strategy. The basiclogistic configuration has to ensure that the

    configuration aspects of PPCprocesses, objects,

    functions and responsibilitiesare consistent with

    each other as well as the achieved prioritisation of

    logistic objectives. The selection of suitable produc-

    tion planning and control methods and algorithms

    facilitates a partially or fully automated materials

    and capacity dispatch. The analyses of the stum-

    bling blocks of PPC offer instructions on how to

    Minimum delivery time

    Mean throughput time

    Criterion: Time

    Planning tolerance

    Variation of throughput times

    Criterion: Tolerance

    Demand fluctuation

    Capacity flexibility

    Criterion: Quantity

    Delivery/lead time

    Lead time

    Time

    Units/day

    Capacityflexibility

    Demandfluctuation

    Distributionof lead times

    Quantity

    Requireddelivery

    time

    Variation ofthroughput times

    Quantity

    Planningtolerance

    Figure 11. Criteria for choice of logistic guideline.

    648 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    16/18

    avoid inconsistencies of the configuration aspects

    of the PPC system.

    . The third stage is the implementation concept of

    the PPC system. This includes the selection of

    PPC software that is capable of supporting the

    technical concept, the setting of all relevant para-

    meters in the PPC software and the development ofa suitable implementation strategy that includes

    the qualification of all staff. Case studies confirm

    the necessity of a role-specific training-on-the-job

    implementation (Wiendahl and Westka mper 2004).

    It is not sufficient to configure a PPC system once on

    implementation. As a rule, changes to the internal and

    external situation of the company require a periodic

    verification in accordance with the PPC cycle shown in

    figure 6. This ensures that the current configuration, the

    methods used and the parameters set are still suitable.

    Two types of changes can be distinguished:

    . Abrupt changes, such as the introduction or with-

    drawal of competitive products, the development of

    new technologies or other changes to the market

    environment are relatively easy to detect. In such

    cases, the need for action is obvious. From a logis-

    tic perspective there is no need for new methods or

    tools for detecting such changes. Timely indicators

    of market or technological changes are desirable.

    These, however, are research issues for general

    management disciplines.

    . Creeping changes are much more difficult to detect.

    Step-by-step adjustments of market volumes,

    delivery or replenishment times hardly attract theattention of those responsible. However, for the

    configuration of PPC systems this type of change

    is much more critical because it necessitates

    the continuous verification and adjustment of the

    chosen configuration in parallel to day-to-day

    business. It can be compared to the sharpening of

    tools that a good craftsman regularly carries out.

    5. Conclusions

    The discussion of the stumbling blocks presented above

    highlights the importance of a holistic configuration of

    PPC systems. Although section 4 outlines the main

    phases of a methodical PPC configuration process,

    a fail-safe procedure has not been developed in

    detail yet. However, as focussed questionnaires are a

    way of assessing the appropriateness of management

    and production system designs (Barnes and

    Rowbotham 2003), the following questions can be

    recommended as part of a quick-check to assess the

    suitability of a chosen configuration. The questions are

    separated into five sections:

    Objectives and stakeholder interests:

    . Have the logistic objectives been defined and are the

    objectives consistent? Is their degree of fulfilment

    being monitored?. Is someone responsible for the fulfilment of the

    objectives?

    . Have the logistic objectives been matched to

    customer demands and are they consistent with

    the performance targets for the employees on all

    hierarchical levels (the stakeholders)?

    Logistic guideline and PPC methods:

    . Does a logistic guideline exist?

    . Do the planning and control methods used match

    the logistic guideline?

    . Is there a mechanism that ensures the consistency

    of logistic guideline, logistic positioning and theplanning and control methods used? Is someone

    responsible for this mechanism?

    Order processing chain and responsibilities:

    . Have the separate process steps of the order

    processing chain been defined?

    . Has the responsibility for each step been assigned?

    . Have the interfaces between the responsibilities

    been defined unambiguously?

    . Do those who have to fulfil the logistic objectives

    have an adequate level of authority for making

    decisions?

    Data quality and parameter setting:

    . Is there a mechanism that ensures the accuracy of

    master data and feedback data? Is someone

    responsible for this mechanism?

    . Are the values of the planned throughput times

    consistent across all three scheduling levels of the

    PPC system (long-range and intermediate-range

    planning, and short-term control)?

    . Is there a mechanism for continuously checking,

    and adapting if necessary, the accuracy of PPC

    parameters? Is someone responsible for this

    mechanism?Qualification of employees and logistics audit:

    . Do all staff involved in the logistics function under-

    stand the fundamental interdependencies between

    the logistic objectives, the manipulated variables

    and the observed variables? Is there a regular

    refresh activity?

    . Does a logistics audit form part of the quality

    management system?

    Stumbling blocks of PPC 649

  • 8/14/2019 Case Study Wiendahl_2005

    17/18

    From a practical point of view, the answers a com-

    pany provides to the questions above directly indicate

    areas that the company has to improve in order to

    achieve a holistic PPC configuration and to avoid the

    stumbling blocks described.

    From a scientific point of view, further research has to

    be carried out in order to adapt the organisational andhuman aspects of existing performance management

    theories to the field of production management and

    integrate them into the framework for configuring

    PPC systems.

    Acknowledgements

    This article reports on research activities of the pro-

    ject Modellbasierte Auftragsmanagement-Gestaltung

    (Model-based Configuration of the Order Management

    Process) that is funded by the German Research

    Foundation (DFG) under registration WI 2670/1.

    References

    Akkermanns, H. and van Helden, K., Vicious and virtuouscycles in ERP implementation: a case study of interrelationsbetween critical success factors. Euro. J. Inform. Syst., 2002,11, 3546.

    Amoako-Gyampah, K., ERP implementation factors: Acomparison of managerial and end-user perspectives.Business Proc. Manage. J., 2004, 2(10), 171183.

    Balve, P., Wiendahl, H.-H. and Westka mper, E., Ordermanagement in transformable business structuresbasics

    and concepts. Robot. Comp.-Integ. Manuf., 2001, 6(17),461468.

    Barnes, D. and Rowbotham, F., Developing a questionnairefor the four-stage model of operations strategy. Prod.Planning & Control, 2003, 7(14), 613622.

    Beckert, B. and Hudetz, W., Stand und Potenzialproduktionsnaher Datenverarbeitung. PPS Manage., 2002,2(7), 3539.

    Davenport, T., Putting the enterprise into the enterprisesystem. 1998, Harv. Business Rev., 4(78), 121131.

    Deming, W.E., Out of Crisis, 18th edition, 1992 (MIT Press:Cambridge).

    Fraunhofer IPT Institute, Droege & Co., Stellhebel furden MarkterfolgBranchenanalyse Maschinenbau, 2003(Droege: Du sseldorf).

    Fogarty, D.W., Blackstone, J.H. and Hoffmann, T.R.,Production and Inventory Management, 2nd edition, 1991(South-Western: Cincinnati).

    Gutenberg, E., Grundlagen der Betriebswirtschaftslehre: Band1: Die Produktion, 1st edition, 1951 (Springer: Berlin).

    Hackstein, R., Produktionsplanung und -steuerung (PPS): EinHandbuch fur die Betriebspraxis. 2nd revised edition, 1989(Springer: Berlin).

    Hopp, W.J. and Spearman, M.L., Factory Physics:Foundations of Manufacturing Management, 2000 (Irwin:Chicago).

    Huczynski, A. and Buchanan, D., Organizational Behaviour:An Introductory Text, 1991 (Prentice Hall: HemelHempstead).

    Kaplan, R. and Norton, D.P., The Balanced Scorecard:Translating Strategy into Action, 1996 (McGraw-Hill:New York).

    Ketokivi, M. and Heikkila , J., A strategic management system

    for manufacturing: Linking action to performance.Prod. Planning & Control, 2003, 6(14), 487496.Kettner, H. and Bechte, W., Neue Wege der Fertigungssteuer-

    ung durch belastungsorientierte Auftragsfreigabe. VDI-Z,1981, 11(123), 459465.

    Kraemmerand, P., Mller, C. and Boer, H., ERP implementa-tion: an integrated process of radical change and continuouslearning. Prod. Planning & Control, 2003, 4(14), 338348.

    Lo dding, H., Verfahren der Fertigungssteuerung, 2004(Springer: Berlin).

    Luczak, H., Eversheim, W. and Schotten, M. (eds.),Produktionsplanung und -steuerung. Grundlagen, Gestaltungund Konzepte, 2nd edition, 1999 (Springer: Berlin).

    Maslow, A.H., Motivation and Personality, 3rd edition, 1987(Addison-Wesley: Boston).

    Mather, H. and Plossl, G.W., Priority fixation versus through-put planning, in Proceedings of the APICS InternationalConference, 1977, pp. 2751.

    Miles, R. and Snow, C.C., Organizational Strategy, Structureand Process, 1978 (McGraw-Hill: New York).

    Nyhuis, P. and Wiendahl, H.-P., Logistische Kennlinien:Grundlagen, Werkzeuge und Anwendungen, 2nd edition,2003 (Springer: Berlin).

    Nyhuis, P., 3-Sigma PPCA holistic approach for managingthe logistic performance of production systems. Ann. CIRP,2004, 1(53), 371376.

    Orlicky, J., Material Requirements Planning, 1975 (McGraw-Hill: New York).

    Plossl, G.W., Production and Inventory Control: Principles andTechniques, 2nd edition, 1985 (Prentice Hall: Englewood

    Cliffs).Plossl, G.W., Managing in the New World of Manufacturing,1991 (Englewood Cliffs: Prentice Hall).

    Riise, J.O. and Johansen, J., Developing a manufacturingvision. Prod. Planning & Control, 2003, 4(14), 327337.

    Stadtler, H., Supply chain managementan overview.In Supply Chain Management and Advanced Planning, editedby H. Stadtler and C. Kilger, pp. 727, 2002 (Springer:Berlin).

    Storey, J. and Sisson, K., Managing Human Resources andIndustrial Relations, 1993 (Open University Press:Buckingham, UK).

    Supply Chain Council, Supply Chain Operations ReferenceModel Version 6.01. Available online at: http://www.supply-chain.org (accessed 1 November 2004).

    Soder, J., 2004, Produktion im Kundentakt. In ManagementCircle Seminar, Munich, 2425 April 2004.

    Vollmann, T.E., Berry, W.L. and Whybark, D.C.,Manufacturing Planning and Control Systems, 4th edition,1997 (Dow Jones-Irwin: Homewood).

    Wa fler, T., 2003, Shop-floor planning and control froma socio-technical perspective. In Current Trends inProduction Management: Proceedings of IFIP WG5.7International Working Conference, 59 October 2003,Karlsruhe, Germany, edited by G. Zu lch, S. Stowasserand H. Jagdev, pp. 94100, 2003 (Shaker: Aachen).

    650 H.-H. Wiendahl et al.

  • 8/14/2019 Case Study Wiendahl_2005

    18/18

    Wiendahl, H.-H., Rempp, B., Westka mper, E. andPritschow, G., PPC in a turbulent environmentfundamen-tals and approaches. In Proceedings of the 33rd CIRPInternational Seminar of Manufacturing Systems, 57June 2000, Stockholm, Sweden, edited by G. Sohlenius,pp. 320325, 2000.

    Wiendahl, H.-H., Situative Konfiguration des Auftragsmanage-ments im turbulenten Umfeld. Heimsheim, 2002 (Jost-Jetter:Stuttgart).

    Wiendahl, H.-H., Roth, N. and Westka mpfer, E., Logisticalpositioning in a turbulent environment. CIRP Ann. Manuf.Tech., 2002, 1(51), 383386.

    Wiendahl, H.-H., Marktanforderungen verstehen,Stolpersteine erkennen. Flexible atmende Produktion:Auftragsschwankungen in den Griff bekommen. InManagement Circle Seminar, Munich, 1718September, 2003a.

    Wiendahl, H.-H., Das logistische Leitbild: Neues Gestaltungs-merkmal der Produktion. Wt Werkstattstechnik, 2003b,4(93), 315322.

    Wiendahl, H.-H. and Westka mper, E., PPC Design andhuman aspects: Training-on-the-job enhances role-specificskills. Prod. Eng., 2004, 1(11), 129132.

    Wiendahl, H.-P., Load-oriented Manufacturing Control, 1995(Springer: Berlin).

    Wiendahl, H.-P., Begemann, C. and Nickel, R., Die klassischenStolpersteine der PPS und der Lo sungsansatz 3-Sigma-PPS.In Expertensystem Logistik, edited by H.-P. Wiendahl andH. Luczak, 2003 (Springer: Berlin).

    Wiendahl, H.-P., von Cieminski, G., Begemann, C. andNickel, R., Human factors in production planning andcontrol. In Integrating Human Aspects in ProductionManagement, edited by G. Zu lch, H. Jagdev and P. Stock,2005 (Springer: Berlin) pp. 113126.

    Wiers, V.C.S., A case study on the integration of APS andERP in a steel processing plant. Prod. Planning & Control,2002, 6(13), 552560.

    Xu, H., Horn Nord, J., Brown, N. and Nord, G.D., Dataquality issues in implementing an ERP. Indust. Manage. &Data Syst., 2002, 102(1), 4758.

    Hans-Hermann Wiendahl studied Industrial Engineering at the Technical University in Berlin.He has worked at the Fraunhofer Institute for Manufacturing Engineering and Automation(IPA) and at the Institute for Industrial Manufacturing and Management (IFF), University ofStuttgart, since 1996 where he held positions as researcher, department manager and now tech-nical manager Order Management. He completed his PhD under the supervision of ProfessorWestka mpfer and is now working on his habilitation thesis. His main research interests are inproduction management, especially PPC, as well as in the selection and implementation of ERPand MES systems. He was responsible for numerous research and industrial projects and haspublished on these subjects extensively.

    Gregor von Cieminski holds a degree in Manufacturing Sciences and Engineering from theUniversity of Strathclyde in Glasgow. He is a research assistant at the Institute of ProductionSystems and Logistics (IFA) at the University of Hannover. As a member of the

    production management research group his interests are in the fields of logistic modelling ofproduction processes and supply chain management. He has published several articles on thesesubjects in scientific journals and conference proceedings.

    Hans-Peter Wiendahlstudied Mechanical Engineering at the Engineering School in Dortmund, atthe RWTH in Aachen and MIT (USA). Under the supervision of Professor Opitz, he completedhis PhD in 1970 and his habilitation thesis in 1972. Until 1979 he was manager of planning andquality at Sulzer Escher Wyss GmbH in Ravensburg before becoming the head of paper machin-ery design for the same company. He became professor and head of the Institute of ProductionSystems and Logistics (IFA) at the University of Hannover in 1979 and held this position until2003. His main research interests are in production management, factory planning and produc-tion systems. He is the author and publisher of numerous books and articles on these subjects.

    Stumbling blocks of PPC 651